We continue to improve Sprint 2 software quality while the Sprint 3 release Beta Testing is starting this week:

  • Validated the S2 release again and approved all fixes OMBU made based on our reported defects.  There is only one outstanding hot bug to be fixed.
  • OMBU demonstrated Sprint 3 release and deployed it for testing on Monday (11/21/16).  Also, test instructions (including video) were in place to guide Beta Testing.
  • OMBU plans to merge some Phase 3 and Phase 1 work together with an extra sprint in Phase 1 (to be completed by Jan 2017).  This would allow OMBU to complete all Data Model work during the CRM development phase.  We are assessing the risks and determing our next steps