We are making great progress on data migration, but stalling on Sprint 4 this week:

  • All major defects reported for the Sprint 2 release have been fixed and verified. The Sprint 2 release is officially accepted by Mazamas!
  • Created draft data migration templates to facilitate both classes (education) and activity data curation work.
  • The Sprint 4 demo and software deployment was delayed from Dec. 8 to Dec. 13 due to illness on the OMBU team in WW48.