June 22, 2017 Update from Peter

images

 

 

 

 

 

by: Peter Tung, IT Project Manager, Encore SVP Fellow

We continue to make great progress on Web UX Visual Design & Data Migration this week. However, the project schedule for our targeted Jan 2018 product launch is at risk. OMBU will propose and review a new work plan to bring in the schedule next week.

  • Data Migration: OMBU has fixed most problems reported by us during the Data Migration validate. New Data Migration Software has been deployed and executed.   Also, OMBU is committed to doing 4 addtional rounds of Data Migration (Aug 17, Oct 17, Dec 17, Jan 18) to capture most recent data and fix problems before our product launch in Jan 2018.
  • Web Ux Design: OMBU has completed their Home Page Redesign and it was well received by Mazamas stakeholders. The final Mazamas feedback was provided to OMBU.
  • Overall Project Schedule: OMBU has delayed the launch schedule to Feb 2018 (one month after the target product launch date). OMBU is working on plans to pull the schedule in.  We will review the new plan on June 27, 2017.

Leave a Reply

Your email address will not be published. Required fields are marked *